| + | =Autonomous Systems Test Arena (building 330D)= |
| | | |
| Our new facility for cooperating autonomous systems - in air, on the ground, on water and below the water surface. | | Our new facility for cooperating autonomous systems - in air, on the ground, on water and below the water surface. |
| | | |
| + | [[File:asta_as_of_06_apr_2020_1.jpg | 450px]] |
| | | |
− | [[File:artist-impression.png | 600px]]
| + | ===Status=== |
− | | + | |
− | Rambøl - expected view of building from the south - operational March 2020.
| + | |
− | | + | |
− | === Sub-pages=== | + | |
− | | + | |
− | * [[Fence blocks]] - former Autonomous Eco-car fence
| + | |
− | | + | |
− | * [[Drone net]] - drone net mounting
| + | |
− | | + | |
− | ===Sketch of building 330D ===
| + | |
− | | + | |
− | [[File:ASTA-onshape-drawing_02.png | 500px]]...
| + | |
− | [[File:ASTA-overview-21-oct-2019.png | 500px]]
| + | |
− | | + | |
− | Overall sketch of the facility, an air dome, about 24 x 40m (960 m^2) with a roof height of 14m.
| + | |
− | The dome is divided into 3 sections with drone net. In one end is a pool 3.5 x 6.5 x 3m deep and in the same area a camera localization system for accurate ground truth localization.
| + | |
− | | + | |
− | | + | |
− | ===Plan===
| + | |
− | | + | |
− | Grand opening - not decided yet
| + | |
− | | + | |
− | week 10-11 (2 Mar to 13 Mar: Finalize pool and electricity installations.
| + | |
− | Start of the final installation of office cabin, storage, camera truss and drone net.
| + | |
− | | + | |
− | week 8-9 (17 Feb to 28 Feb) Installation and inflation of Dome.
| + | |
− | | + | |
− | Week 5-7 (27 Jan to 14 Feb) Pool installation, levelling and Asphalt. Asphalt is a 9cm GAB layer (GAB is Gravel, Asfalt (Asphalt), and Beton (Concrete)).
| + | |
− | | + | |
− | Next week (20 to 24 Jan): Wells, drain and piping (inside the building).
| + | |
− | | + | |
− | === Current state ===
| + | |
− | | + | |
− | ====January 2020====
| + | |
− | | + | |
− | [[File:asta_as_of_17_jan_2020_1.jpg | 400px]]
| + | |
− | | + | |
− | As of 17 Jan 2020. The site is (almost) cleared for levelling before asphalt.
| + | |
− | | + | |
− | [[File:asta_as_of_15_jan_2020_2.jpg | 400px]]
| + | |
− | [[File:asta_as_of_15_jan_2020_1.jpg | 400px]]
| + | |
− | | + | |
− | As of 15 Jan 2020. Entrance by vehicles are slight to the left of the "main" road and is now visible. The pool is now isolated and in the process of being backfilled.
| + | |
− | | + | |
− | [[File:asta_as_of_13_jan_2020_1.jpg | 400px]]
| + | |
− | | + | |
− | As of 13 Jan 2020. Entrance platforms are cast, now the only concrete that remains is a small platform for the ventilation (the square to the right).
| + | |
− | | + | |
− | [[File:asta_as_of_08_jan_2020_1.jpg | 400px]]
| + | |
− | | + | |
− | As of 8 Jan 2020. The platform at the entrance (picture) as well as the emergency exit, fans and port are being prepared.
| + | |
− | | + | |
− | ====December 2019 ====
| + | |
− | | + | |
− | [[File:asta_as_of_30_dec_2019_1.jpg | 400px]]
| + | |
− | | + | |
− | As of 30 Dec 2019. Quit Xmas-times. The water around the pool is clear and still, and the water tower in the background is still there.
| + | |
− | | + | |
− | [[File:asta_as_of_17_dec_2019_1.jpg | 400px]]
| + | |
− | [[File:asta_as_of_20_dec_2019_1.jpg | 400px]]
| + | |
− | | + | |
− | As of 20 Dec 2019. The pool concrete is finished. After some days of hardening, it is to be sealed from groundwater. Then it can be back-filled for asphalt preparation.
| + | |
− | | + | |
− | [[File:asta_as_of_16_dec_2019_2.jpg | 400px]]
| + | |
− | | + | |
− | As of 16 Dec 2019. The concrete form is being removed and the pool concrete starts showing.
| + | |
− | | + | |
− | [[File:asta_as_of_12_dec_2019_4.jpg | 400px]]
| + | |
− | | + | |
− | [[File:asta_as_of_12_dec_2019_1.jpg | 400px]]
| + | |
− | [[File:asta_as_of_12_dec_2019_2.jpg | 400px]]
| + | |
− | | + | |
− | | + | |
− | As of 12 Dec 2019. Reinforcement - almost - in place, sides will be cast Friday (13 Dec 2019)
| + | |
− | | + | |
− | | + | |
− | [[File:asta_as_of_10_dec_2019.jpg | 400px]]
| + | |
− | | + | |
− | As of 10 Dec 2019. Reinforcement in stainless steel for the pool sides is being built.
| + | |
− | | + | |
− | [[File:asta_as_of_09_dec_2019.jpg | 400px]]
| + | |
− | | + | |
− | As of 9 Dec 2019. The pool is on its way, the bottom plate is cast.
| + | |
− | | + | |
− | | + | |
− | [[File:asta_as_of_04_dec_2019_1.jpg | 400px]]
| + | |
− | [[File:asta_as_of_04_dec_2019_2.jpg | 400px]]
| + | |
− | | + | |
− | As of 4 Dec 2019. All quiet, waiting for the pool people.
| + | |
− | | + | |
− | | + | |
− | After that the indoor asphalt and foundation for entrance, gate and emergency exits.
| + | |
− | | + | |
− | ====November 2019 ====
| + | |
− | | + | |
− | [[File:asta_as_of_27_nov_2019_pool_base.jpg | 400px]]
| + | |
− | [[File:asta_as_of_27_nov_2019_outside_drain.jpg | 400px]]
| + | |
− | | + | |
− | As of 27 Nov 2019. The pool pit is finished and a clean base for the pool is in place. The outside drain is in progress.
| + | |
− | | + | |
− | [[File:asta_as_of_22_nov_2019_pool_corner.jpg | 400px]]
| + | |
− | | + | |
− | As of 22 Nov 2019. Pool pit progressing and preparing for the outside drain.
| + | |
− | | + | |
− | [[File:asta_as_of_20_nov_2019.jpg | 400px]]
| + | |
− | [[File:asta_as_of_20_nov_2019_entrance_cast.jpg | 400px]]
| + | |
− | | + | |
− | As of 20 Nov 2019. Pool pit started and final part of the foundation (entrance) cast.
| + | |
− | | + | |
− | | + | |
− | [[File:asta_as_of_18_nov_2019.jpg | 400px]]
| + | |
− | | + | |
− | As of 18 Nov 2019. The foundation looks good and excavating for the pool has started. The plan is to cast the entrance on Wednesday and the bottom of the pool-hole on Friday, ready for the pool team on Monday 27 Nov.
| + | |
− | | + | |
− | | + | |
− | [[File:asta_as_of_14_nov_2019.jpg | 400px]]
| + | |
− | [[File:asta_as_of_14_nov_2019_entrance.jpg | 400px]]
| + | |
− | | + | |
− | As of 14 Nov 2019. Most of the foundation is now cast and the form is being removed. The casting of the entrance part of the foundation is being prepared.
| + | |
| | | |
| + | 28 June 2021: |
| + | Fully operational (:D) |
| | | |
| + | === Instructions === |
| | | |
− | [[File:asta_as_of_11_nov_2019.jpg | 400px]] | + | * [[ASTA access]] - instruction for access |
| | | |
− | As of 11 Nov 2019. The final height of foundation being marked and in-door floor levelling in the background (before asphalt) - except for pool area (upper left).
| + | * [[ASTA pool]] - instructions for pool use and maintenance. |
| | | |
− | [[File:asta_as_of_8_nov_2019_before_pool.jpg | 400px]] | + | * [[ASTA motion capture]] - instructions for use |
| | | |
− | As of 8 Nov 2019. Concrete form for foundation cast in place. This is the corner, where the pool is to be placed.
| + | * [[ASTA booking]] - instructions for booking. |
| | | |
− | [[File:asta_as_of_4_nov_2019.png | 400px]]
| + | === ASTA insides === |
| | | |
− | as of 4 Nov 2019. The first level of concrete in place.
| + | * [http://aut.elektro.dtu.dk/rse/ASTA/asta_view.html View to ASTA] (must be on local net (10.59.8/9.x) to work) |
| | | |
− | ====October 2019 ====
| + | * [[Building history]] - pictures from process |
| | | |
− | [[File:fundament_23oct2019.png | 400px]]
| + | ===Maintainer=== |
| | | |
− | as of 23 October 2019. Edge foundation started.
| + | This page is (mainly) maintained by Christian Andersen (jcan@dtu.dk) |
Our new facility for cooperating autonomous systems - in air, on the ground, on water and below the water surface.