ASTA

From Rsewiki
(Difference between revisions)
Jump to: navigation, search
(Autonomous Systems Test Arena)
Line 30: Line 30:
 
as of 4 November 2019. The first level of concrete in place.
 
as of 4 November 2019. The first level of concrete in place.
  
The upper part of the foundation to be cast Monday 11 November.  
+
[[File:asta_as_of_8_nov_2019_before_pool.jpg | 400px]]
 +
 
 +
As of 8 nov 2019. Concreate form for foundation cast in place (to be cast on monday 11 November). This is the corner, where the pool is to be placed.
  
 
Then the pool preparation is next.
 
Then the pool preparation is next.

Revision as of 15:26, 8 November 2019


Autonomous Systems Test Arena

Our new facility for cooperating autonomous systems - in air, on the ground, on water and below water.


Artist-impression.png

Rambøl - expected view of building from the south.

Sketch of building 330D

ASTA-onshape-drawing 02.png

ASTA-overview-21-oct-2019.png

Overall sketch of the facility, an air dome, about 23 x 40m with a roof height of 14m. The dome is divided into 3 sections with drone (removable) net. In one end is a pool 3.3 x 6.5 x 3m and in the same area a camera localization system for accurate ground truth localization.

Current state

Fundament 23oct2019.png

as of 23 October 2019. Edge foundation started.

Asta as of 4 nov 2019.png

as of 4 November 2019. The first level of concrete in place.

Asta as of 8 nov 2019 before pool.jpg

As of 8 nov 2019. Concreate form for foundation cast in place (to be cast on monday 11 November). This is the corner, where the pool is to be placed.

Then the pool preparation is next.

After that the indoor asphalt and foundation for entrance, gate and emergency exits.

Dome delivery and mounting in January 2019.

Dome inflation and in-door preparation in February 2020.