ASTA

From Rsewiki
(Difference between revisions)
Jump to: navigation, search
(Sketch of building 330D)
(Current state)
Line 47: Line 47:
 
[[File:asta_as_of_14_nov_2019_entrance.jpg | 400px]]
 
[[File:asta_as_of_14_nov_2019_entrance.jpg | 400px]]
  
As of 14 nov 2019. Most of the foundation is now cast and the form beeing removed. The casting of the entrance part of the foundation is being prepared.
+
As of 14 nov 2019. Most of the foundation is now cast and the form is being removed. The casting of the entrance part of the foundation is being prepared.
 +
 
 +
[[File:asta_as_of_18_nov_2019.jpg | 400px]]
 +
 
 +
As of 18 Nov 2019. The foundation looks good and excavating for the pool has started.
  
 
Then the pool preparation and outside drainage are next.
 
Then the pool preparation and outside drainage are next.

Revision as of 14:12, 18 November 2019


Die asta.png (jyllands-posten.dk)

Contents

Autonomous Systems Test Arena

Our new facility for cooperating autonomous systems - in air, on the ground, on water and below water.


Artist-impression.png Asta as of 8 nov 2019.jpg

Rambøl - expected view of building from the south and current view (8 Nov 2019).

Sub-pages

Sketch of building 330D

ASTA-onshape-drawing 02.png... ASTA-overview-21-oct-2019.png

Overall sketch of the facility, an air dome, about 23 x 40m with a roof height of 14m. The dome is divided into 3 sections with drone (removable) net. In one end is a pool 3.5 x 6.5 x 3m deep and in the same area a camera localization system for accurate ground truth localization.

Current state

Fundament 23oct2019.png

as of 23 October 2019. Edge foundation started.

Asta as of 4 nov 2019.png

as of 4 November 2019. The first level of concrete in place.

Asta as of 8 nov 2019 before pool.jpg

As of 8 nov 2019. Concrete form for foundation cast in place. This is the corner, where the pool is to be placed.

Asta as of 11 nov 2019.jpg

As of 11 nov 2019. The final height of foundation being marked and in-door floor levelling in the background (before asphalt) - except for pool area (upper left).

Asta as of 14 nov 2019.jpg Asta as of 14 nov 2019 entrance.jpg

As of 14 nov 2019. Most of the foundation is now cast and the form is being removed. The casting of the entrance part of the foundation is being prepared.

Asta as of 18 nov 2019.jpg

As of 18 Nov 2019. The foundation looks good and excavating for the pool has started.

Then the pool preparation and outside drainage are next.

After that the indoor asphalt and foundation for entrance, gate and emergency exits.

Dome delivery and mounting in January 2020.

Dome inflation and in-door preparation in February 2020.

This page is maintained by jca@elektro.dtu.dk