ASTA

From Rsewiki
(Difference between revisions)
Jump to: navigation, search
(January 2020)
(Current state)
Line 41: Line 41:
  
 
====January 2020====
 
====January 2020====
 +
 +
[[File:asta_as_of_29_jan_2020_1.jpg | 400px]]
 +
 +
As of 29 Jan 2020. Heating to keep ASTA frost-free using DTU district heating is beeing prepared.
  
 
[[File:asta_as_of_22_jan_2020_1.jpg | 400px]]
 
[[File:asta_as_of_22_jan_2020_1.jpg | 400px]]

Revision as of 11:53, 29 January 2020


Die asta.png (jyllands-posten.dk)

Contents

Autonomous Systems Test Arena

Our new facility for cooperating autonomous systems - in air, on the ground, on water and below the water surface.


Artist-impression.png

Rambøl - expected view of building from the south - operational March 2020.

Sub-pages

Sketch of building 330D

ASTA-onshape-drawing 02.png... ASTA-overview-21-oct-2019.png

Overall sketch of the facility, an air dome, about 24 x 40m (960 m^2) with a roof height of 14m. The dome is divided into 3 sections with drone net. In one end is a pool 3.5 x 6.5 x 3m deep and in the same area a camera localization system for accurate ground truth localization.


Plan

Grand opening - not decided yet

week 10-11 (2 Mar to 13 Mar: Finalize pool and electricity installations. Start of the final installation of office cabin, storage, camera truss and drone net.

week 8-9 (17 Feb to 28 Feb) Installation and inflation of Dome.

Week 5-7 (27 Jan to 14 Feb) Pool installation, levelling and Asphalt. Asphalt is a 9cm GAB layer (GAB is Grus (Gravel), Asfalt (Asphalt), and Beton (Concrete)).

Current state

January 2020

Asta as of 29 jan 2020 1.jpg

As of 29 Jan 2020. Heating to keep ASTA frost-free using DTU district heating is beeing prepared.

Asta as of 22 jan 2020 1.jpg

As of 22 Jan 2020. Levelling of terrain, so that the asphalt will be at the same level as the rim foundation (Foto Michael Cole).

Asta as of 21 jan 2020 1.jpg

As of 21 Jan 2020. Pool backfilling is finished, including pipe and drainage. And we now can have a first look into the pool.

Asta as of 17 jan 2020 1.jpg

As of 17 Jan 2020. The site is (almost) cleared for levelling before asphalt.

Asta as of 15 jan 2020 2.jpg Asta as of 15 jan 2020 1.jpg

As of 15 Jan 2020. Entrance by vehicles are slight to the left of the "main" road and is now visible. The pool is now isolated and in the process of being backfilled.

Asta as of 13 jan 2020 1.jpg

As of 13 Jan 2020. Entrance platforms are cast, now the only concrete that remains is a small platform for the ventilation (the square to the right).

Asta as of 08 jan 2020 1.jpg

As of 8 Jan 2020. The platform at the entrance (picture) as well as the emergency exit, fans and port are being prepared.

December 2019

Asta as of 30 dec 2019 1.jpg

As of 30 Dec 2019. Quit Xmas-times. The water around the pool is clear and still, and the water tower in the background is still there.

Asta as of 17 dec 2019 1.jpg Asta as of 20 dec 2019 1.jpg

As of 20 Dec 2019. The pool concrete is finished. After some days of hardening, it is to be sealed from groundwater. Then it can be back-filled for asphalt preparation.

Asta as of 16 dec 2019 2.jpg

As of 16 Dec 2019. The concrete form is being removed and the pool concrete starts showing.

Asta as of 12 dec 2019 4.jpg

Asta as of 12 dec 2019 1.jpg Asta as of 12 dec 2019 2.jpg


As of 12 Dec 2019. Reinforcement - almost - in place, sides will be cast Friday (13 Dec 2019)


Asta as of 10 dec 2019.jpg

As of 10 Dec 2019. Reinforcement in stainless steel for the pool sides is being built.

Asta as of 09 dec 2019.jpg

As of 9 Dec 2019. The pool is on its way, the bottom plate is cast.


Asta as of 04 dec 2019 1.jpg Asta as of 04 dec 2019 2.jpg

As of 4 Dec 2019. All quiet, waiting for the pool people.


After that the indoor asphalt and foundation for entrance, gate and emergency exits.

November 2019

Asta as of 27 nov 2019 pool base.jpg Asta as of 27 nov 2019 outside drain.jpg

As of 27 Nov 2019. The pool pit is finished and a clean base for the pool is in place. The outside drain is in progress.

Asta as of 22 nov 2019 pool corner.jpg

As of 22 Nov 2019. Pool pit progressing and preparing for the outside drain.

Asta as of 20 nov 2019.jpg Asta as of 20 nov 2019 entrance cast.jpg

As of 20 Nov 2019. Pool pit started and final part of the foundation (entrance) cast.


Asta as of 18 nov 2019.jpg

As of 18 Nov 2019. The foundation looks good and excavating for the pool has started. The plan is to cast the entrance on Wednesday and the bottom of the pool-hole on Friday, ready for the pool team on Monday 27 Nov.


Asta as of 14 nov 2019.jpg Asta as of 14 nov 2019 entrance.jpg

As of 14 Nov 2019. Most of the foundation is now cast and the form is being removed. The casting of the entrance part of the foundation is being prepared.


Asta as of 11 nov 2019.jpg

As of 11 Nov 2019. The final height of foundation being marked and in-door floor levelling in the background (before asphalt) - except for pool area (upper left).

Asta as of 8 nov 2019 before pool.jpg

As of 8 Nov 2019. Concrete form for foundation cast in place. This is the corner, where the pool is to be placed.

Asta as of 4 nov 2019.png

as of 4 Nov 2019. The first level of concrete in place.

October 2019

Fundament 23oct2019.png

as of 23 October 2019. Edge foundation started.

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox